๐Ÿ“š Legal Insights ยท Civil Law ยท Contracts

The Legal Impact of Force Majeure on Contractual Obligations in the UAE

August 2026 ยท Civil Law ยท 14 min read ยท Ahmad Abdulla Ahli Advocates & Legal Consultants

Quick Answer: Under UAE law, force majeure may relieve a contracting party from performance where an external event beyond the party's control makes performance genuinely impossible โ€” not merely more difficult, expensive or commercially unattractive. Under Federal Decree-Law No. 25 of 2025 Promulgating the Civil Transactions Law, which came into force on 1 June 2026, Article 236 addresses the consequences of force majeure in bilateral contracts. Where performance remains possible but has become exceptionally burdensome, that falls within the exceptional-circumstances or hardship doctrine under Article 224, rather than classic force majeure.

What Is Force Majeure Under UAE Law?

War, natural disasters, government restrictions, widespread transport disruption or other extraordinary events may interfere with contractual performance. UAE law recognises that in certain circumstances it would be unjust โ€” or legally impossible โ€” to require a party to perform an obligation that has become impossible because of an event outside that party's control. Force majeure does not, however, provide a general escape route from an unfavourable contract. The central question is usually not "did an extraordinary event occur?" but "did that event actually make the particular contractual obligation impossible to perform?"

Important 2026 Change: A New Civil Transactions Law

Many existing articles and contracts still refer to Federal Law No. 5 of 1985. That is no longer the current legislation โ€” the UAE enacted Federal Decree-Law No. 25 of 2025 Promulgating the Civil Transactions Law, which took effect on 1 June 2026 and repealed the 1985 Code. Under the former Code, Article 273 dealt with force majeure and impossibility, and Article 287 addressed damage caused by an external cause. Under the current law: Article 236 principally addresses force majeure in bilateral contracts; Article 224 addresses exceptional circumstances and onerous obligations; Article 249 addresses exemption from liability for damage caused by an external cause; Article 336 addresses compensation where performance becomes impossible; and Article 428 provides for extinction of an obligation where the debtor proves performance became impossible because of an external cause beyond the debtor's control.

What Are the Essential Elements of Force Majeure?

Merely labelling something a "force majeure event" is insufficient. The party invoking the doctrine must establish:

War is not automatically force majeure for every contract merely because a conflict exists somewhere in the region โ€” the party must demonstrate how the conflict directly made its own obligation impossible. Likewise, a pandemic, government restriction or supply-chain interruption does not automatically qualify.

Article 236: Total, Partial and Temporary Impossibility

Total impossibility: where force majeure makes performance of an obligation completely impossible in a bilateral contract, Article 236 provides that the corresponding obligations are extinguished and the contract is rescinded automatically.

Partial impossibility: where only part of the obligation becomes impossible, either party may rely on extinction of the obligation for the impossible part or seek judicial rescission of the contract, preventing an unnecessarily rigid all-or-nothing approach.

Temporary impossibility in continuous contracts: Article 236 also permits either party to rely on extinction of the corresponding obligation, seek modification of the contract, or request judicial rescission โ€” particularly relevant to continuing supply contracts, service agreements and other long-term arrangements.

Force Majeure Is Different From Hardship

Force majeure generally concerns impossibility of performance. Article 224 concerns a different situation, applying where unforeseen exceptional circumstances of a public nature make performance onerous enough to threaten the debtor with severe loss, even though performance has not necessarily become impossible. Where Article 224 applies, the court may โ€” after balancing the interests of both parties โ€” reduce the onerous obligation to a reasonable level or order rescission of the contract. An agreement contrary to this statutory protection is void.

For example: if importation of specified material becomes legally and objectively impossible, that may raise a force-majeure issue. If the material can still legally be obtained but extraordinary circumstances increase the cost so dramatically that performance threatens severe loss, that may instead be an Article 224 exceptional-circumstances issue. Ordinary inflation, market movement, loss of profit or commercial miscalculation should not automatically be characterised as force majeure.

Liability for Damages

Article 249 provides, in the context of harmful acts, that where a person proves damage arose from an external cause beyond that person's control โ€” including a natural calamity, sudden event, force majeure, or the act of another person โ€” the person is not liable for compensation unless legislation or an agreement provides otherwise. Article 336 provides that where a debtor cannot perform an obligation specifically, compensation may ordinarily become due for non-performance, but the debtor may avoid that liability by proving that impossibility arose from an external cause beyond its control.

Who Has the Burden of Proving Force Majeure?

The party relying on force majeure should be prepared to prove it. Article 428 places emphasis on the debtor establishing that performance became impossible because of an external cause beyond its control. A party seeking force-majeure relief should preserve evidence of the event, why it was unforeseeable and unavoidable, the contractual obligation affected, the causal connection, mitigation steps taken and notices sent to the counterparty. Simply stating that "force majeure occurred" will rarely be enough in a serious dispute.

Does the Contract's Force Majeure Clause Matter?

Absolutely. Before relying solely on the general provisions of the Civil Transactions Law, the parties should examine the contract carefully โ€” a detailed clause may address what constitutes a qualifying event, excluded events, notice requirements and deadlines, obligations to mitigate, suspension of performance, extension of time, continued payment obligations, and termination after prolonged force majeure. Article 221 requires contracts to be performed in accordance with their contents and consistently with the requirements of good faith โ€” a party should not use a disruptive event opportunistically to escape obligations that remain perfectly capable of performance.

Practical Steps for Businesses Facing a Potential Force Majeure Event

Force majeure remains an important protection within UAE contract law, but it should not be treated as a general excuse for poor performance or an unprofitable transaction. Parties should avoid treating the words "force majeure" as a conclusion in themselves โ€” the event, causation, impossibility, contractual wording and evidence are what ultimately matter. Our Civil Law team advises businesses on force majeure, hardship and contract disputes under the new Civil Transactions Law โ€” read more about our Civil Law practice.

Frequently Asked Questions

Force majeure generally refers to an external, uncontrollable event that makes performance of a contractual obligation impossible. Under the current UAE Civil Transactions Law, Article 236 addresses force majeure in bilateral contracts where performance becomes impossible.
As of 1 June 2026, the principal federal Civil Code is Federal Decree-Law No. 25 of 2025 Promulgating the Civil Transactions Law, which replaced Federal Law No. 5 of 1985.
No. Article 273 belongs to the former Federal Law No. 5 of 1985. Under the current Civil Transactions Law, the principal equivalent provision dealing with force majeure in bilateral contracts is Article 236.
Force majeure under Article 236 concerns impossibility of performance. Article 224 deals with unforeseen exceptional circumstances that make performance severely onerous while still possible, threatening the debtor with serious loss.
Increased price alone does not ordinarily establish impossibility. Where performance remains possible but has become exceptionally burdensome, Article 224 may be more relevant depending on the circumstances.
Not in every situation. Under Article 236, total impossibility in a bilateral contract can result in automatic rescission, while partial and temporary impossibility are treated differently and can give rise to other remedies.
Article 236 allows either contracting party, in a case of partial impossibility, to rely on extinction of the corresponding obligation or seek judicial rescission, subject to the circumstances.
For temporary impossibility in continuous contracts, Article 236 provides mechanisms including reliance on extinction of the corresponding obligation, modification or seeking judicial rescission.
The party relying on the defence should be prepared to prove the facts establishing it. Article 428 expressly refers to the debtor proving that performance became impossible because of an external cause beyond its control.
Not automatically. The Federal Supreme Court has previously rejected an asphalt-production plant breakdown as force majeure where the failure could have been anticipated and prevented through appropriate care.
Potentially, but not automatically. The party must still show that the particular event and its consequences satisfy the contractual and legal requirements and actually made the relevant obligation impossible โ€” the existence of a wider crisis alone is not sufficient.
Yes. A carefully drafted clause can define qualifying events, establish notice requirements, allocate costs, provide extensions of time and determine when prolonged disruption permits termination, substantially reducing uncertainty.